Project update – Surrey

By May 10, 2017WTT News

We are very pleased to announce that in Surrey all the installation works are finished.

The preparations for the start-up of the Biofuel Facility have been started.

The cold commissioning is planned for the coming period and will be followed by hot commissioning with the first waste around summer 2017.

The facility is planned to be fully operational at the end of 2017.

We will keep you updated!